CIRED 2017. Session 1: Network components

CIRED 2017. Session 1: Network components

12-15 Июня 2017, Глазго, Шотландия.

ТемаАвторы
0049Offline PD diagnostics using several excitation voltagesH Putter, F Petzold, P Legler, Megger, Germany
0056On line monitoring of medium voltage overhead distribution lines polluted insulators severityO E Gouda, Cairo University, Egypt, D M Khalifa, Egyptian Electricity Transmission Company, Egypt
0107ABC cables in colour other than blackZ Pamić, HEP ODS d.o.o. ELEKTRA ZAGREB, Croatia
0114Parameters of influence on LV cable ageingQ De Clerck, J M Meunier, Laborelec, Belgium, J Van Slycken, Eandis, Belgium, M Van Den Berg, Sibelga, Belgium, P Colin, Ores, Belgium
0200Investigations on the mechanical and electrical behavior of HTLS conductors by accelerated ageing testsC Kϋhnel, S Grossmann, IEEH TU Dresden, Germany, R Bardl, D Stengel, BAM Berlin, Germany, W Kiewitt, 50Hertz Transmission GmbH, Germany
0260Medium voltage shielded busbar long term ageing test methodK Helal, R Maladen, F Gentils, O Kozlova, Schneider Electric, France
0266External conductive layer on EDP MV underground cables leads to new oversheath requirementsE Francisco, J Cruz, J Silva, F Costeira, EDP Distribuição, Portugal
0270Integration challenges of high accuracy LPIT into MV recloserB Kerr, N Uzelac, GandW Electric Co., United States, L Peretto, University of Bologna, Italy, E Scala, Altea S.r.l., Italy
0272Design of MV overhead lines to maximise bird safetyA Beutel, B McLaren, H Geldenhuys, N Khoza, R Kruger, R Branfied, Eskom Holdings SOC Ltd, South Africa, J Van Coller, University of the Witwatersrand, South Africa, C Hoogstad, Endangered Wildlife Trust, South Africa
0279Anti-ice and snow coating for EDP Distribuição's overhead linesR Bernardo, J Cardoso, R Catalão, EDP Distribuição, Portugal, L Ilharco, IST-CQFM, Portugal
0291Sensitivity analysis of cable oscillating wave test system on multi-source defects diagnosticsG Lu, G Wu, J Xiong, Y Liu, Guangzhou Power Supply, China
0414Self-healing materials for autonomous cable repairR RhodesI German, S Basu, G C Stevens, Gnosys Global Ltd., United Kingdom
0418Determining cables metrics using 3D ultrasonic scanningS Sutton, University of Southampton, United Kingdom, P Willmott, Acuity Products Ltd, United Kingdom
0430The use of high temperature conductors in existing lines: economic and environmental benefitsL Moreira, A Lopes, EDP-Distribuição, Portugal
0532Investigation of partial discharge frequency dependence in distribution system cablesT S Negm, M Refaey, A A Hossam-Eldin, University of Alexandria, Egypt
0537Evaluation of aging degradation of 6kV CV cable (three-layer co-extruded structure)M Kobayashi, M Kuze, Chubu Electric Power Company, Japan, T Fuseya, TOENEC Corporation, Japan
059810 Years of experience with 3 kHz water tree testM Burceanu, Q De Clerck, Y Tits, Laborelec, Belgium
0602An innovative power cable connection of property equivalence and non-jointH Zhong, Y Xia, Z Liang, CYG Electric Technology Co., Ltd. China
0797Analysis and evaluation of dielectric parameters for design verification and calibration of a newly developed diagnostic system for MV power cablesF Eppelein, C Weindl, Coburg University of Applied Sciences, Germany, I Mladenovic, Siemens AG, Germany
0813Measurement results of a spatially-resolved diagnostic method and influencing factors in field environment of MV power cablesE Fischer, C Weindl, Coburg University of Applied Sciences, Germany
0826Experiences with cable faults located at metallic screen connectionsH L Halvorson, S Hvidsten, H Kulbotten, J K Lervik, SINTEF Energy Research, Norway
0893Long-time evaluation of cable joints in waterM Dreßler, S Kornhuber, University of Applied Science Zittau/Görlitz, Germany, G Jacob, Behr Bircher Cellpack BBC Radeberg GmbH, Germany, B Knüpfer, Cellpack GmbH, Germany
0912New HVDC nanocomposite electrical insulation for improved MV and HVAC performanceN Freebody, G Stevens, Gnosys Global Ltd, United Kingdom, A Vaughan, University of Southampton, United Kingdom, F Perrot, A Hyde, GE Grid Solutions, United Kingdom
0917High performance thermoplastic cable insulation systemsA Pye, G Stevens, Gnosys Global Ltd, United Kingdom
1066Using nanomaterial to enhance the performance of medium voltage insulators and street lights considering environmental impactsM Fazaee, M Abdoli, Tehran University, Iran, B Jamshidieini, AEPDC, Iran/Tehran University, Iran, N Eskandari, AEPDC, Iran
1108Sensitivity analysis of earthing system impedance for single and multilayered SoilV Vycital, D Topolanek, P Toman, M Ptacek, Brno University of Technology, Czech Republic
1130Underground and Overhead Monitoring Systems for MV Distribution SystemsF Zavoda, IREQ (Hydro-Quebec), Canada, E Rodriguez, 3M, United States, G C Fofeldea, 3M, Canada
1134Developement of long-term reliability evaluation method for polypropylene insulated MV cablesY Jung, D Kim, B Lee, S Lee, KEPCO, Korea
0091Comparative advantage of using GRP in compact substationsC Martinez Nieto, D Tϋrk, A Palgi, ABB, Estonia
0138Proven reliability beyond the standardsI OrueI Gilbert, J Larrieta, S Sebastian, Ormazabal, Spain
0212New HV/LV transformer substation within building intended for other non electrical uses with advanced functionalitiesJ Cormenzana, S Sebastian, Ormazabal, Spain
0220Mastering all sub-assemblies of an MV circuit-breaker and racking truck system ensures reliability and robustnessD Serve, T Milan, C Mombard, J P Meley, E Frangin, Schneider Electric, France
0229DC vacuum circuit breakerL Liljestrand, M Backman, L Jonsson, ABB, Sweden, M Riva, ABB, Italy, E Dullni, ABB, Germany
0230Environmental and safety aspects of AirPlus insulated GISM Hyrenbach, ABB AG, Germany, T A Paul, ABB Ltd, Switzerland, J Owens, 3M Company, United States
0244Safety features in the design of MV circuit-breakers and switchboardsD Fulchiron, J-P Meley, P Pulfer, Schneider-Electric, France
0250Transferred charge: indicator for vacuum applicabilityM Leusenkamp, Eaton, China, G C Schoonenberg, Eaton, Netherlands
0253Innovative underground distribution cabinet for low voltage networkN Santos, M Lagarto, C Rodrigues, EDP Distribuição, Portugal
0345Influence of heat source location on the air temperatures in sealed MV switchgearE Fjeld, W Rondeel, K Vaagsaether, University College of Southeast Norway, Norway, E Attar, ABB, Norway
0349Estimating the temperature rise of load break switch contacts in enclosed MV switchgearE Fjeld, W Rondeel, S T Hagen, University College of Southeast Norway, Norway, M Saxegaard, ABB, Norway
0371Mitigate gas combustion in case of internal arcJ Douchin, Schneider Electric, France, Y Cressault, Toulouse University, France, R Danjoux, FLIR, France
0372Extreme weather has become the norm - is your MV switchgear ready for it?K Tandel, Schneider Electric, India, T Cormenier, Schneider Electric, France
0385Hazard study of MV switchgear with SF6 alternative gas in electrical roomC Preve, R Maladen, Schneider Electric, France, G Lahaye, T Penelon, INERIS, France, M Richaud, S Galas, Universite De Montpellier, France
0389Application of HFO1234zeE in MV switchgear as SF6 alternative gasC Preve, R Maladen, Schneider Electric, France, D Piccoz, Piccoz SASU, France
0475Meeting ecodesign efficiency requirements: ensuring accuracy in power transformer loss tests via TLM system calibrationsG Rietveld, E Houtzager, M Acanski, D Hoogenboom, VSL, Netherlands
0486Pressure oscillation due to arcs in a closed container filled with air and SF6M Kotari, T Tadokoro, S I Tanaka, M Iwata, Central Research Institute of Electric Power Industry, Japan
0604Comparative study on arc extinction process under air, CO2 and SF6 gas blasting using two-dimensional electron density imaging sensorY Inada, Saitama University, Japan, S Yamaguchi, A Kumada, H Ikeda, K Hidaka, The University of Tokyo, Japan, T Nakano, K Murai, Y Tanaka, Kanazawa University, Japan
0614Low-current interruption in SF6-alternativesM Saxegaard, E Attar, M Kristoffersen, H Landsverk, O Granhaug, ABB, Norway, A Di-Gianni, S Scheel, ABB, Switzerland
0658RMU with eco-efficient gas mixtures: field experienceM Kristoffersen, T Endre, M Saxegaard, P A Wang, ABB, Norway, M Hyrenbach, ABB, Germany, D Harmsen, T V Rijn, R Vosse, Liander, Netherlands
0767Mitigate arc effects within an E-houseJ Douchin, A Clavel, Schneider Electric, France, A Brown, Schneider Electric, Singapore, J Rintala, Schneider Electric, Finland
0795Characteristics of g3 - an alternative to SF6Y Kieffel, F Biquez, D Vigouroux, P Ponchon, GE Grid Solutuions, France, A Schlernitzauer, R Magous, G Cros, University of Montpellier, France, J G Owens, 3M, United States
0819Holistic evaluation of the performance of today's SF6 alternatives proposalsS Kosse, P G Nikolic, G Kachelriess, Siemens AG, Germany
0852Stress on outer cable connection of MV gas insulated switchgear due to cable thermal expansion at rated currentJ Snajdr, R Huck, P Novak, Schneider Electric, Germany, J P Bentley, Schneider Electric, France
0872Difference between switching of motors and generators with vacuum technologyK R Venna, H Urbanek, N Anger, Siemens AG, Germany
0943Developing testing procedures for high voltage innovation technologiesD Hardman, N Murdoch, WSP | Parsons Brinckerhoff, United Kingdom, J Berry, Western Power Distribution, United Kingdom
1069How to select auxiliary relays for isolation applicationsN Calvo Cuadra, S Rementeria, Arteche, Spain, R Calister, Arteche, Brazil
1100Power hardware-in-the-loop setup for power system stability analysesR Brandl, T Degner, Fraunhofer IWES, Germany, M Calin, DERlab e.V., Germany
1268A high short-circuit impedance power transformer versus short-circuit limiting reactanceM Zouiti, Enedis, France, A Kirche, O Moreau, EDF, France
0004Introducing the new product line of regulated distribution transformer Cooperation of Siemens AG and A. Eberle GmbH and Co. KG.S H Hoppert, A Eberle GmbH and Co. KG., Germany, L K Kelemen, Z N Nádudvari, G V Vörös, Siemens, Hungary
0086Power router based on conventional three phase bridge inverter and DC-DC converterL Ren, C Zhang, M Du, Tianjin University of Technology, China
0110Field trial results of power electronics in LV distribution networksC Newton, S C Terry, Ricardo Energy and Environment, United Kingdom, P Lang, UK Power Networks, United Kingdom
0137A novel micro PMU for distribution power linesX Wang, X Xie, S Zhang, L Luo, Y Liu, G Sheng, X Jiang, Shanghai Jiao Tong University (SJTU), China, X Cheng, Beijing Electric Power Research Institute, China
0207Line voltage regulator based on magnetic-controlled inductors for low voltage gridsM Holt, J Maasmann, C Rehtanz, TU Dortmund University, Germany
0226Fault sensorsM Scarabeli, G Ortenzi, J Aith, Elektro, Brazil
0328Managing the maturity of decision-support data for extending lives of MV cablesQ Zhuang, GEIRI Europe SGCC, Germany, J Janssen, N Steentjes, Liander, Netherlands
0348Beyond grid integration of renewables - Voltage Regulation Distribution Transformers (VRDT) in public grids, at industrial sites, and as part of generation unitsM Sojer, W Hofer, Maschinenfabrik Reinhausen GmbH, Germany
0391Compatibility of a G3PLC telecom solution on a three phase 230 V networkH Halluin, H Grandjean, ORES, Belgium, G Ethève, Enedis, France, A Jeandin, EDF RandD, France
0413Contribution of augmented reality to the maintenance of network equipmentM Cordonnier, S Martino, C Boisseau, S Paslier, J P Recapet, F Blanc, Enedis, France, B Augustin, EDF RandD, France
0417Evaluation of the mountability of the medium voltage accessoriesH Tanzeghti, A Kirche, Enedis, France
0479Maintenance of street lights by climbing robots in Alborz Electric Power Distribution CompanyN Eskandari, M Rafiei, E Abooei, AEPCS, Iran, B Jamshidieini, AEPCS, Iran, Tehran University, Iran
0519LVDC RULES - technical specifications for public LVDC distribution networkP Nuutinen, T Kaipia, J Karppanen, A Mattsson, A Lana, A Pinomaa, P Peltoniemi, J Partanen, Lappeenranta University of Technology (LUT), Finland, M Luukkanen, Ensto Finland Oy, Finland, T Hakala, Elenia Oy, Finland
0546Accurate on-line fault location and PD activity location results obtained with SCG - a long term utility experienceD Harmsen, S Lamboo, F Van Minnen, Alliander, Netherlands, P Wagenaars, DNV GL, Netherlands
0681Using smart grid sensors and advanced software applications as an asset management tool at Hydro OttawaD Sabin, Electrotek Concepts, United States, G MacLeod, Current Power Services, Canada, M Wojdan, Hydro Ottawa, Canada
0709Sensor technology in a medium voltage switchgear for the US market applicationsP Milovac, IEM, United States, R Javora, ABB, Czech Republic, V Skendzic, SEL, United States
0715Continous safeguarding of rating accuracyM Olschewski, P Schaefer, W Hill, LIOS Technology GmbH, Germany
0737Improve the reliability of MV underground links by using long cableH Tanzeghti, Enedis, France, Y Brument, F Gaillard, EDF RandD, France
0820Full-scale case study of a road crossing thermal bottleneck in a buried MV cable installationE Eberg, S M Hellesø, S Hvidsten, SINTEF Energy Research, Norway, K Espeland, REN AS, Norway
0832A new smart distribution transformer with OLTC for low carbon technologies integrationL Del Río Etayo, A Soto, A Ulasenka, ORMAZABAL Corporate Technology, Spain, P Lauzevis, ENEDIS, France, P Cirujano, G Perez De Nanclares, ORMAZABAL COTRADIS, Spain
0835Opportunities to use satellite technologies for asset condition monitoring of power networks under the European Space Agency's Integrated Applications Promotion (IAP) programmeI Downey, ESA IAP Ambassador Platform, United Kingdom, M Segovia, C Harrison, University of Strathclyde, United Kingdom
0882Low-power voltage transformers for use with separable connectors in MV secondary gas insulated switchgear - new challenge for standardisationR Javora, V Prokop, ABB s.r.o., Czech Republic, E De Ridder, S Mensaert, Nexans, Belgium
0895Analysis of failure in power cables for preventing power outage in Alexandria Electricity Distribution Company in EgyptA Attia, Alexandria Electricity Distribution Company, Egypt
0922Cyclic rating of wind farm cable connectionsR Chippendale, J Pilgrim, University of Southampton, United Kingdom, A Kazerooni, WSP | Parsons Brinckerhoff, United Kingdom, D Ruthven, SP Energy Networks, United Kingdom
0933Complete MV-BPL communications solution for large AMI and grid automation deploymentsJ Aguirre Valparis, A Amezua, J A Sanchez, Ormazabal, Spain, A Sendin, J Simon, Iberdrola, Spain, S Dominiak, HSLU, Sitzerland
0941Steady-state modelling for the integration of a bi-directional AC-DC-AC flexible power linkJ King, N Murdoch, WSP | Parsons Brinckerhoff, United Kingdom, J Berry, Western Power Distribution, United Kingdom
1048Information and communication architecture for transmission power line inspections using unmanned aircraft systemR Z Homma, Celesc, Brazil, C SzymanskiInerge/Evoluma, Brazil, R Ávila Faraco, Inerge/Unisul, Brazil
1104Improving reliability by focusing on the quality and condition of medium voltage cables and cable accessoriesO Siirto, J Vepsäläinen, A Hämäläinen, M Loukkalahti, Helen Electricity Network Ltd, Finland
1193Analysis of the recognition and localisation techniques of power transmission lines components in aerial images acquired by dronesR Z Homma, Celesc, Brazil, O SohnR C Bose, INERGE, Brazil
1215Survey of market prospects and standardisation development needs of LVDC technologyT Kaipia, Lappeenranta University of Technology, Finland, P Sebellin, International Electrotechnical Commission, Switzerland, V Mahendru, Legrand India, India, K Hirose, NTT Facilities, Japan, W De Kesel, Legrand Group, Belgium, G Luber, R Pelta, Siemens AG, Germany, D Goswami, Bureau of Indian Standards, India
0008Improvement of duval triangle 1S Spremić, EPS Technical Centre Novi Sad, Serbia
0039Battery anomaly and degradation diagnosis for renewable energy plantJ Zhang, L Geng, Y Ma, Hitachi (China) Research and Development Corporation, China
0042Dealing with in-field repair tasks of large power transformersJ L Martínez, Edenor, Argentina
0103Monitoring systems for secondary substations - a comparative studyJ Johansson, H Sporre, L Selberg, O Hansson, Ellevio AB, Sweden
0149Combining statistics and physics to rank circuit breakers on conditionE Tazelaar, D Breteler, J van Tongeren, Alliander, Netherlands, R Stijl, Bearing Point, Netherlands
0206Analysis of rusty closed type switchgearsK Morii, Kansai Electric Power Co. Inc. Japan
0263Smart asset management using online monitoringD Courtney, Embedded Monitoring Systems, United Kingdom, J Livie, Scottish Power Energy Networks, United Kingdom, T Littler, Queen's University, United Kingdom
0273Design and demonstration of a wireless sensor network platform for substation asset managementN T Huynh, ECE Associates Ltd, United Kingdom, V Robu, D Flynn, Heriot-Watt University, United Kingdom, S Rowland, G Coapes, Siemens, United Kingdom
0283Experience of the applications of FRA methodology to evaluate short-circuit tests in distribution transformersD Tourn, S Nesci, J C Gomez, L Sanchez, UNRC, Argentina
0296Frequency response analysis for exact power transformer impedanceM Hiraide, T Nakajima, T Koshizuka, Tokyo Denki University, Japan, H Ikeda, Y Taniguchi, E Haginomori, The University of Tokyo, Japan, N Harid, N Al Sayari, B Barkat, A Devadiga, The Petroleum Institute, United Arab Emirates
0322How to control the impact of the severe environments surrounding medium voltage switchgearT Cormenier, P Veuillet, V Ferraro, Schneider Electric, France
0326An innovative approach towards an algorithm for automated defect recognition for on-load tap changersF Riaz, J Wetzer, DNV GL Energy, Netherlands, A Rodrigo Mor, TU Delft, Netherlands
0415Modular online monitoring system to allow condition based maintenance for medium voltage switchgearK Perdon, M Scarpellini, S Magoni, L Cavalli, ABB S.p.A, Italy
0445Maximise asset availability and reduce maintenance costs - an integrated approach combining condition assessment with data analyticsA Hauser, B Fenski, ABB AG, Germany, L Cavalli, ABB SpA, Italy
0539Comparisons of transformer top oil temperature calculation models using support vector regression optimised by genetic algorithmT Qian, W H Tang, W J Jin, South China University of Technology, China, L Gan, Y Q Liu, G J Lu, Guangzhou Power Supply Co. Ltd., Guangzhou, China
0541Fault diagnosis of high-voltage circuit breakers using wavelet packet technique and support vector machineW J Jin, W H Tang, T Qian, T Y Ji, South China University of Technology, Guangzhou, China, L Gan, Y Q Liu, G J Lu, Guangzhou Power Supply Co. Ltd., China
0657Data analysis of battery storage systemsM Andoni, W Tang, V Robu, D Flynn, Heriot Watt University, United Kingdom
0665Evaluation of lifetime of air insulated switchgear versus service conditions in MV substationsY Tits, H Van Lijsebeth, Laborelec, Belgium, W Demaesschalck, W Van Vaerenbergh, Eandis, Belgium, P Thiry, Ores, Belgium, B Godeau, Elia, Belgium, M van den Berg, Sibelga, Belgium
0698Design and successful utilisation of the first multi-purpose mobile distributed energy storage system in IranN Nakhodchi, N Aghli, S Alishahi, M H Pourarab, MEEDC, Iran
0703Reliability measures: failure and root cause analysis (FRCA) for GIS early failureM Lee, M Park, Y Kim, LSIS, South Korea
0752A novel approach for wide area real time health condition assessment of the power circuit breakersL Maruša, A Souvent, S Vižintin, EIMV, Slovenia, R Maruša, ELES d.o.o., Slovenia
0774Analysis of condition and risk based maintenance planning for MV/LV substationsP Köhn, A Schnettler, RWTH Aachen University, Germany, N Schultze, SAG GmbH, Germany
0796Switchgear operating personnel safety upgrade solutions for aged installed baseC Gemme, P Bassi, G Magno, ABB, Italy
0839Advance control and monitoring in secondary substation - project UPGRIDS Noske, D Falkowski, ENERGA-OPERATOR SA, Poland, A Babs, Institute of Power Engineering, Poland
0840New soft sensors for distribution transformer monitoringJ F Tissier, J Cornet, ITRON, France
0846SPEN switchgear life extension strategyA Santandreu, D Neilson, SP Energy Networks, United Kingdom
0876Management and easy communication of temperature rise on distribution cast resin transformers connections linked to network during the life of transformer and/or after installationA Hammen, G Ranalletta, C Macri, Schneider Electric, France
0894Field testing of a wideband monitoring concept at MV side of secondary substationB A Siddiqui, P Pakonen, P Verho, TUT, Finland
0952Power and asset monitoring strategy to facilitate a smart networkA Elena de Leonardo, K Lennon, A Beddoes, M Bebbington, SP Energy Networks, United Kingdom
0989Natural esters for life and capacity enhancement of distribution transformersR Pillai, F Havaldar, C Chitnis, The Tata Power Company Ltd, India
1001Economical and practicable condition assessment of MV- and LV- distribution gridsC Johae, D Beerboom, E Pawlowski, M Zdrallek, Wuppertal University, Germany, N Schultze, SAG GmbH, Germany, R Timmreck, Stadtwerke Iserlohn GmbH, Germany
1053Application of enhanced thermal ratings to primary substation transformersI Elders, K Bell, University of Strathclyde, United Kindgom, K Smith, A Collinson, Scottish Power Energy Networks, United Kingdom
1078Teardown of a compact distribution transformer after twelve years of severe loading conditionsV Vasconcellos, CPFL Energia, Brazil, A Sbravati, Cargill CIS, Brazil, K J Rapp, Cargill CIS, United States, L C Zanetta Jr, PEA USP, Brazil
1098Improving Asset Management with Online Partial Discharge Monitoring of Ring Main Units and Secondary SubstationsC Eastham, D Longo, K Tavernier, L Pickford, IPEC Ltd., United Kingdom
1102Experimental study of dynamic thermal behaviour of an 11 kV distribution transformerR Villarroel, Q Liu, Z Wang, The University of Manchester, United Kingdom
1174Health index as condition estimator for power system equipment: A critical discussion and case studyJ H Jürgensen, A Scheutz Godin, P Hilber, KTH, Sweden
1262Power transformer’s monitoring system for better asset managementS Ceferin, G Janc, Kolektor Sisteh d.o.o., Slovenia, Z Toroš, T Kastelic, Elektro Primorska d.d., Slovenia, B Prašnikar, Kolektor Etra d.o.o., Slovenia
1308Managing on-load tap changer life cycle in TNB Distribution Power TransformersY Z Yang Ghazali, Tenaga Nasional Berhad, Malaysia